Schedule and location
The project schedule will be updated as the project development progresses.
2022
EIA and master planning underway
2023
Finalizing master planning proposal and EIA-report
2024
Approved master plan
Building permits
2025
Construction work
Ajankohtaista
- 10/2022 – Public events regarding the EIA program were held on 18-20.10. in Ylivieska, Alavieska, and Kalajoki.
- 11/2021 – The city of Kalajoki has approved the zoning initiative for the Verkasalo project.
- 05/2021 – The city of Ylivieska has approved the zoning initiative for the Verkasalo project.
- 04/2021 – The municipality of Alavieska has approved the zoning initiative for the Verkasalo project.
More information about the project’s EIA-process: Verkasalon tuulivoimahanke (Ympäristö.fi)
![](https://winda.fi/wp-content/uploads/2023/11/verkasalo-kartta-nettiin2-1024x512.jpg)
Contact
![](https://winda.fi/wp-content/uploads/2023/10/Edgar-1.png)
Edgar Kekkonen
Project Manager
edgar.kekkonen@winda.fi
+358 40 168 6937
![](https://winda.fi/wp-content/uploads/2023/11/Mika-Vihela.jpg)
Paikallisedustus
Mika Vihelä
Local partner
mika.vihela@gmail.com