Development phase

Ukonkangas – Puolanka

Wind power |
Winda Energy is planning a wind farm in Ukonkangas, Puolanka. The project area is initially approximately 1600 hectares in size, located in the southwestern part of Puolanka, about 2 km east of Puokio. Preliminary plans include the construction of up to 12-16 wind turbines for the area. The exact number and placement of turbines will be specified through discussions with landowners and the zoning process. In addition to zoning, an environmental impact assessment procedure (EIA) will be conducted for the area.
12-16
turbines
1600
hectare

Schedule and location

The project schedule will be updated as the project development progresses.

2023

EIA and Master planning underway

2024

EIA and Master planning underway

Finalizing master planning proposal

Approved master plan

2025

Building permits

Start of construction work

2026

Construction work

Current news

  • The next public event will be organized in early spring 2024.
  • A public event was held at Puolankajärvi School on 27.11.2023.
  • A public event was held at Puolankajärvi School on 22.2.2023.
  • 06/2022 – A public meeting regarding the EIA program was held on 13.6. in Puolanka
  • 11/2021 – The municipality of Puolanka approved the zoning initiative for the Ukonkangas project

More information about the project’s EIA-process: Ympäristöhallinto.fi (Ukonkangas)



Contact

Landowner Contact Person

Hannu Haavisto
Land Use Specialist & Team Lead
hannu.haavisto@winda.fi
+358 40 502 8853

Project Manager

Edgar Kekkonen
Project Manager
edgar.kekkonen@winda.fi
+358 40 168 6937

Local Partner

Tuomo Tamminen
Local partner
raahentuulivoimaconsulting@gmail.com