Development phase

Siltaneva – Teuva

Wind power |
Winda Energy is planning a wind farm in Siltaneva, Teuva. The project area is initially approximately 1000 hectares in size, located in the northern part of Teuva near the border with Kurikka. Preliminary plans include around 8 wind turbines for the area. The exact number and placement of turbines will be specified through discussions with landowners and the zoning process. In addition to zoning, an environmental impact assessment procedure (EIA) will be conducted for the area.
8
turbines
64 MW
total power
1000
hectare

Schedule and location

2024

Participation and assessment scheme

EIA-program

 

2025

EIA-report

Master Plan draft

2026

Master Plan proposal

Building permits

Start of construction