Schedule and location
The project schedule will be updated as the project development progresses.
2023
EIA and Master planning underway
2024
EIA and Master planning underway
2025
EIA and Master planning underway
Finalizing master planning proposal
Approved master plan
2026
Building permits
Start of construction work
2027
Construction work
Current news
- The first public event will be organized early next year of 2024.
- 6/2023 The city of Vaala approved the zoning initiative for the Susisuo project.
Contact
Landowner Contact Person
Hannu Haavisto
Land Use Specialist & Team Lead
hannu.haavisto@winda.fi
+358 40 502 8853
Project Manager
Edgar Kekkonen
Project Manager
edgar.kekkonen@winda.fi
+358 40 168 6937